吸收塔钢格栅板的安装方法
吸收塔钢格栅板的安装方法:将钢格栅板固定在对应的框架上,直接安装在锅炉上的钢格栅板,要按照层次选择不同规格的钢格栅板逐级排列,方便吊到设计好的位置。在铺设的时候,用不同规格的钢格栅板铺设在相对应的框架上,分布均匀然后焊接固定,产品支垫处的平面要垂直平整,误差在0.5mm以内。在现场拼接的时候要保证产品的在一条直线,弯曲度应在1%范围以内,铺设方向要一致。在需要切割的部分,应按照图纸的要求进行局部加强。
The installation method of steel grille plate for absorption tower is to fix steel grille plate on the corresponding frame and directly install the steel grille plate on the boiler. The steel grille plates with different specifications should be arranged step by step according to the level, so as to hang to the designed location conveniently. When laying, the steel grid plates with different specifications are laid on the corresponding frames, distributed evenly, then welded and fixed. The plane of the products supporting pad should be vertical and flat, and the error is within 0.5mm. In the scene stitching to ensure that the product in a straight line, the bending degree should be within the 1% range, the laying direction should be consistent. In the parts that need to be cut, local reinforcement should be carried out in accordance with the requirements of the drawings.